Day Two – Wednesday 24th May 2017

007:00 hours – Pre-start

07:10 hours – commencement of works (plastic up east fence and south fence).

10:30 hours – commence scraping top of block of grass and top soil

12:00 hours – detailed inspection of work area, no asbestos fragments found.

Weather:

Morning light winds south easterly building from 15 to 20 km/h to 20 to 30 km/h in the afternoon then becoming light in the evening.

Air Sampling:

Calibrator – Defender 510 s/n #9014

Cowl 001 pump #8214 at 1451 mL/minute
Cowl 002 pump #8214 at 1468 mL/minute
Cowl 003 pump #7149 at 1445 mL/minute

Real Time Dust Monitoring PM10s:

Upwind typically less than 0.075 mg/m3
Downwind typically less than 0.075 mg/m3

13:30 hours – failure of hydraulic hose on excavator

14:50 hours – recommence of works using excavator.

No incidences observered or reported.