Month: June 2017
Day 18 – Tuesday 27th June, 2017

Day 17 – Monday 26th June, 2017
Pre-start 06:50 hours
Start 07:00 hours (repair damage done to black plastic on fences)
Plane delayed arrived 09:30 hours.
Daily Report:

Day 16 – Friday 23rd June, 2017
Pre-start 06:50 hours
Work Commences 07:00 hours
Daily Report:

Day 15 – Thursday 22nd June, 2017
Pre-start 06:10 hours
Commencement of Works 07:00 hours
Daily Report:

Day 14 – Wednesday 21st June, 2017
Pre-start 07:00 hours
Commencement of Works: 07:10 hours
Air Monitoring:
031 #8214 WT North 2021 2018 1974 7:45 16:30
032 #0518 WT South West 2012 2014 1961 7:45 16:31
033 #7149 WT Front Gate 2014 2021 1961 7:45 16:31
Daily Report:

Day 13 – Tuesday 20th June 2017
Pre-start: 07:00 hours
Work Commencing: 07:10 hours
029 #8214 WT North 2018 2014 1974 7:45 16:30
030 #0518 WT South West 2018 2024 1961 7:45 16:31
Daily Report:

Day 12 – Monday19th June 2017
Per-start Meeting 08:15 hours
Work commencing 08:30 hours.
Air Monitoring:
027 #8214 WT North 2012 2016 1974 7:45 16:30
028 #0518 WT South West 2026 2010 1961 7:45 16:31
Daily Report:

Day Eleven – Wednesday14th June 2017
06:55 hours – pre-start meeting
07:00 hours – inspection of worksite, all clear
07:05 hours – commencement of works
Day Ten – Tuesday 13th June 2017
06:50 hours – Pre-start
07:00 hours – Commencement of Works
Air Sampling:
Calibrator – Defender 510 s/n #9014
Cowl Pump Type Location Flow Rates Time on and off:
023 #8214 WT North 2010 1922 07:05 16:30
024 #0518 WT South West 2011 1922 07:05 16:31
Weather:
Southernly 5 to 15 kms
Fine and Sunny
Daily Report: