Day Nine – Monday 12th June 2017

09:00 hours – Pre-start

09:10 hours – reinstall barricading, move horses out of worksite, and secure fences.

11:45 hours – commencement of works (delay due to waiting on excavator and bucket).

Air Sampling:

Calibrator – Defender 510 s/n #9014

Cowl Pump Type Location Flow Rates Time on and off:
021 #8214 WT North 2020 1929 1974 11:45 16:30
022 #0518 WT South West 2010 1912 1961 11:45 16:31

Weather:

Southernly 5 to 15 kms
Fine and Sunny

Daily Report:

Day Eight – Thursday 1st June 2017

007:00 hours – Pre-start

07:10 hours – commencement of works (sieve using excavator).

Air Sampling:

Calibrator – Defender 510 s/n #9014

Cowl Pump Type Location Flow Rates Time on and off:

019 #8214 WT North 2020 1929 1974 7:04 15:30
020 #0518 WT South West 2010 1912 1961 7:05 15:31

Weather:

Sunny, no breeze during the morning followed by light winds becoming south easterly 12 to 15 km/h in the afternoon then becoming light in the evening.

Fine, no breeze.

Real Time Dust Monitoring PM10s:

Upwind typically less than 0.065 mg/m3
Downwind typically less than 0.065 mg/m3

Daily Report:

Day Seven – Wednesday 31st May 2017

007:00 hours – Pre-start

07:10 hours – commencement of works (sieve using excavator).

Air Sampling:

Calibrator – Defender 510 s/n #9014

Cowl Pump Type Location Flow Rates Time on and off:

016 #8214 WT North 2020 1929 1974 7:04 16:30
017 #0518 WT South West 2010 1912 1961 7:05 16:31
018 #7149 WT South East 2022 1950 1986 7:04 16:35

Weather:

Sunny, no breeze during the morning followed by light winds becoming south easterly 10 to 15 km/h in the afternoon then becoming light in the evening.

Fine, no breeze.

Real Time Dust Monitoring PM10s:

Upwind typically less than 0.055 mg/m3
Downwind typically less than 0.055 mg/m3

Daily Report: